凱德莊園專案進度

凱德莊園專案進度

1

The Square樓棟

歡迎來到The Square第二次專案進度更新, 在這裡能瞭解到建設進度, 建築位址和下一步將採取的的行動。

The Square中離令人驚歎的Cator公園和新裝修的Kidbrooke火車站近在咫尺, 該火車站將於2019年第二季度開放。

我們目前正在按計劃於2018年8月至2019年3月期間交付4棟樓。

英文原文:

The Square is within close proximity to the stunning Cator Park and the newly refurbished, Kidbrooke train station which is due to open in Q2 of 2019. We are currently on schedule to deliver all 4 buildings in The Square from August 2018 to March 2019.

Please see below the current construction progress within each building core.

2

Cottam House & Marsden House樓棟

我們在裝飾裝修階段, 在Cottam House和Marsden House的所有樓層和公共區域。 從下面的圖片中可以看到, 這些建築樓層已經初具規模, 正在按照你的選擇來安裝。


核心A1(Cottam House)外部形象


核心A1(Cottam House)廚房裝修的內部形象。


核心A1(Cottam House)外部形象


核心A1(Cottam House)廚房裝修的內部形象

英文原文:

We are in the decoration stage on all floors and communal areas in Cottam House and Marsden House. As you can see from the images below, the plots are starting to take form and your choices are being installed as per your selection.

3

Hopgood Tower & Patterson Tower樓棟

我們正在完成HopgoodTower的第二個修復階段, 目前在Patterson大廈的低層安裝了浴室和廚房。

在公共區域, 我們目前正在測試服務, 已經完成了天花板邊緣的建造, 並完成幹襯以提升鋒面。


A3 (HopgoodTower)外部圖像


A3 (HopgoodTower)內部圖像


A4 (Patterson Tower)外部圖像


A4 (Patterson Tower)內部圖像

英文原文:

We are in the process of finishing off the second fix phase in Hopgood Tower and currently installing the bathrooms and kitchens on lower floors in Patterson Tower. In the communal areas we are currently testing services, forming ceiling margins and completing dry lining to lift fronts.

4

完工通知書

親愛的投資者, 我們很高興地通知您, 為了您方便瞭解, 我們已經進一步完善了完工日期:

Cottam House (核心A1) - 2018年9月。

Marsden House (Core A2) - 2018年10月/ 11月。

Hopgood Tower(核心A3) - 2019年1月/ 2月/ 3月。

Patternson Tower(核心A4) - 2018年11月/ 12月或2019年1月。

*由於不可預見的情況, 完成日期很不幸必須改變。 如果發生這種情況, 您將會得到通知。

英文原文:

I am delighted to inform you that we have further refined the date to serve notice for completion on your property as follows:

Cottam House (Core A1) - September 2018

Marsden House (Core A2) - October/November 2018

Hopgood Tower (Core A3) - January/February/March 2019

Patternson Tower (Core A4) - November/December 2018 or January 2019

*Due to unforeseen circumstances, completion dates may unfortunately have to change.Should this occur you will be notified.